Create an Expense for a PO

Before paying an expense from the Purchase Order, you will need to create a GL Mapping. 

Go to ADMINISTRATION -> FINANCIAL -> ACCOUNTING -> GL ACCOUNT 

Here we will create a new GL Account.

In our example we will input the following info:

- Name: New Appliance

- Account Type: Expense

- Account Number: Fill in account number here (Example: 5000-8888)

Then SAVE.

Screenshot_2021-04-21_163019.png

Go to ADMINISTRATION -> GL ACCOUNT MAPPING

Select a new GL Account Mapping in EXPENSE tab

- GL Account: select the one just created : "5000-8888 New Appliance"

- Scope level: Default (across the organization)

- Vendor Service: Building/Appliances - New

- Vendor: no need to select an option here

The most important thing here is to select which work is done under a GL Account.

=> Now a new GL Account mapping is created.

Screenshot_2021-04-21_162829.png

Go to FINANCE -> PURCHASING -> PURCHASE ORDER 

Here you will select the PO you have created previously.

Screenshot_2021-04-21_165022.png

Once you are inside the PO, select the line item.

Screenshot_2021-04-21_165144.png

Select the GL Account, we have just created. As an example, here it is 5000-8888 New Appliances. SAVE.

Screenshot_2021-04-21_165424.png

Go to ACTIONS -> SUBMIT.

Screenshot_2021-04-21_165701.png

=> The PO is submitted for the Vendor RBC (See screenshot example).

Go to FINANCE -> EXPENSES -> EXPENSES 

Here we will create a new expense.

Select NEW EXPENSE

Screenshot_2021-04-21_154826.png

In this new expense, you will fill in the following info:

- Vendor: In our example, it is RBC.

- Orders: select the PO related.

- Expense ID: input a number ID

- Expense Date: Select the date

Screenshot_2021-04-21_165902.png

Select SAVE.

Now the line items are edited from the PO selected previously:

Screenshot_2021-04-21_170121.png

 

So far we have submitted the PO but we did not complete it (the work is not done yet).

Once the PO is completed, we will be able to send the invoice to the Vendor.

 

Go to FINANCE -> PURCHASING -> PURCHASE ORDERS

Select the PO concerned

Go to ACTIONS -> COMPLETE

Screenshot_2021-04-21_170516.png

Let's suppose the work is done, input the full amount.

Screenshot_2021-04-21_160319.png

If the work is not fully completed, you will not be able to send the expense!

 

Now that the work is completed, we are able to submit it.

Go back to FINANCE -> EXPENSES -> Select the Expense concerned (RBC)

Select ACTIONS -> SUBMIT

Screenshot_2021-04-21_170645.png

Now that the expense is created you can pay the Vendor. You will have to continue with Payment.

Go to FINANCE -> ACCOUNTING -> GENERAL JOURNAL-> Sort the ID -> Select the Expense concerned

Screenshot_2021-04-21_172523.png

Go to REPORTS -> INCOME STATEMENTS -> New Income Statement Report

Screenshot_2021-04-21_173112.png

Select the Building concerned in filter and click on GENERATE

Here the Expense is displayed.

FYI we see the Income from Tenants who are paying rent.

Screenshot_2021-04-21_173343.png

 

Now we need to do the Payment. We need to send money to the Vendor.

Our system does not have Electronic Payment capability at the moment for Vendors. Instead, to complete this transaction/payment  you will need to select Cheque.

The Expense is now a Charge which needs to be paid.

Go to FINANCE -> ACCOUNTS PAYABLE -> PAY EXPENSES

Select the line and go to the button PAY EXPENSES

Screenshot_2021-04-21_174136.png

Here, the GL Payment Account concerns the AP selected on a Building level.

In our example, the Building B1, 707 Brand Rd, Mixed Residential has an AP (Account Payable).

This AP selects the bank account you are sending money to the Vendor.

Screenshot_2021-04-21_174816.png

Now let's go back to the PAYMENT

Go to FINANCE -> ACCOUNTS PAYABLE -> PAY EXPENSES

Select the line and go to the button PAY EXPENSES.

In Payment Type, select Cheque. Input the amount to pay and select Create PAYMENTS

Select the line and go to ACTIONS -> APPROVE

Screenshot_2021-04-21_175447.png

Now the payment is done.

Go to FINANCE -> EXPENSES -> EXPENSES

Select the one concerned

Go to PAYMENTS AND CREDITS tab

Here we can see the payment is Confirmed.

Screenshot_2021-04-21_175905.png

Go to FINANCE -> ACCOUNTING -> GENERAL JOURNAL

Now we can see the Payment has been done.

Select the line and click on Transaction Ref

Screenshot_2021-04-21_180349.png

Select PRINT CHEQUE 

Screenshot_2021-04-21_180517.png

Now you can download the Cheque Printout and give to your Vendor.

Screenshot_2021-04-21_180637.png

Finally the last step is to Select ACTIONS -> COMPLETE.

Now the Expense is done. No one can modify it.